Steel work on College Park Plaza’s roof for the new chiller units is scheduled to start January 23, 2013.
Here’s what else is happening with the construction work:
- Fireproofing patch work of the steel and metal deck is complete on the fourth and fifth floors; the third floor is scheduled to be finished on January 23.
- Installation of the HW process piping continues on the fourth and fifth floors and in the ramp mechanical room.
- Dry-wall, metal stud, and patch work continues on some walls on the fifth and sixth floors.
- The mechanical contractor is installing new ductwork on the fourth and fifth floors.
Yay! No more chiller noise!