Work to start this week on College Park Plaza’s ‘chiller units’

Steel work on College Park Plaza’s roof for the new chiller units is scheduled to start January 23, 2013.

Here’s what else is happening with the construction work:

  • Fireproofing patch work of the steel and metal deck is complete on the fourth and fifth floors; the third floor is scheduled to be finished on January 23.
  • Installation of the HW process piping continues on the fourth and fifth floors and  in the ramp mechanical room.
  • Dry-wall, metal stud, and patch work continues on some walls on the fifth and sixth floors.
  • The mechanical contractor is installing new ductwork on the fourth and fifth floors.

 

One thought on “Work to start this week on College Park Plaza’s ‘chiller units’

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s