A crane is scheduled to arrive in the Saint Mark’s parking lot, on the south side of College Park Plaza, this week.
Renovations to College Park Plaza include:
- installation of HW process piping on the second and third floors.
- electrical rough-ins and conduit installation in the penthouse and the fifth floor.
- installation of new ductwork on the second floor.
- work on the existing second floor I-beams.
- installation of fire suppression pipe in the ramp-level mechanical room.