Phase 1 of the Main Building project includes fire suppression, HVAC work and a more significant renovation of the second floor to support Business Department instruction. The window replacement project is also well under way around the building!
- Interior work on the third through fifth floors will be complete by the start of the fall semester.
- A portion of the second floor, which includes three new computer labs for the Business Department, will be ready by the start of the fall semester. The west wing will still be closed for a few weeks, and we will move classes into those spaces as soon as possible!
- Window and fire protection work will continue throughout the school year and will be coordinated for evening and weekend activity.